WHEN YOU NEED POWER, FAST

GE can provide you with emergency power delivery, installation and production, no matter where you are in the world. How? It’s what we call fast power.

Whether you need power in 10 days or 10 months, we offer solutions ranging from our trailer-mounted compact power plant on wheels to a larger block of power like the 9E gas turbine.

Our modular power generation offerings can save you valuable construction and lead time as well as capital expenditures. We can deliver your temporary power units faster, install them faster, commission them faster, and can even ramp them up faster. With the ability to go from cold iron to full power in as little as five minutes, our mobile gas turbine, the TM2500, along with our aeroderivative and heavy-duty gas turbines, can rapidly enable power generation in response to sudden demands.

Whether it’s Egypt’s desert climate demanding the need for additional power in the summer, or Greece’s 2 million tourists taxing their power system, GE can provide immediate power solutions to fit your power demands in an emergency.

Don't know where to start?

Our range of power turbines, whether portable and compact or heavy-duty, makes it easy to get the power you need, and our people and services make it even easier for you to get up and running. We offer warranties, detailed operation and maintenance programs, and contractual services throughout your project terms. With over 100 years of power generation experience on our side, we’ve got the knowledge and skill to get you powered up quickly.

Have questions for GE?

image-fast
test

Delivered in weeks: Up to 6x faster than other technology

test

Fast start: At full power in 15 minutes or less

URGENT & MOBILE POWER

When and where you need power, even in emergencies.

CONTACT GE TODAY

LET US HELP IDENTIFY THE POWER SOLUTION THAT BEST MEETS YOUR GROWING NEEDS

If you need temporary power generation within 11 weeks, the trailer-mounted TM2500 aeroderivative mobile gas turbine is right for you. You can receive up to 35MW of power potential per unit, and the portable TM2500 gas turbine can be transported anywhere by land, air, or sea. This mobile gas turbine power plant also runs with many fuel sources, protecting against fuel supply disruptions, price volatility, and fuel adulteration. These modular power generating units can come pre-packaged, providing you with a turnkey design, saving you valuable construction and lead-time, as well as capital expenditures.

Once they’re installed, our gas turbine power units ramp up within 15 minutes, getting you the power production you need quickly.

But even though we get things done quickly, we can offer a partnership that doesn’t stop after your turbine starts up for the first time. Our services include, but aren’t limited to:

  • On-call technical advisory services
  • Maintenance planning and training
  • On-site hot section, combustor, and other modular exchanges
  • Depot repair services for scheduled overhauls and unscheduled repairs
  • Performance testing

FAST-TRACK POWER

Quickly meet your growing grid capacity.


If your electricity demand is outpacing your current capability, we can help you capitalize on your growing needs by helping you with fast-track power. We can dispatch our larger-megawatt gas turbines, and get you up and running in around 6-9 months.

In addition to fast delivery, we also shortened our installation and commissioning times. Our modular packaging and AdvantEDGE Power Island offerings are just two examples of how we’ve built speed and efficiency right into our products. See how we broke records in Egypt.

pipeline_substation_tunisia_450_x_350

FAST POWER PRODUCT PORTFOLIO

Our portfolio of gas turbines help you get up and running—faster than you ever thought possible. Explore all of our options, from the portable TM2500 power plant to the heavy-duty 9E turbine, you can choose which one is right for you.

CONTACT GE TODAY

LET US HELP IDENTIFY THE POWER SOLUTION THAT BEST MEETS YOUR GROWING NEEDS

Power in 1 - 6 Months

Power in 6 - 9 Months

Specifications
TM2500 Mobile Gas Turbine
(50/60 Hz)
LM2500 Flexible Gas Turbine
(50/60 Hz)
LM6000 Ultra-Powerful Gas Turbine
(50/60 Hz)
9E.03/9E.04 Rugged Gas Turbine
(50 Hz)
GT13E2 Fuel-Flexible Gas Turbine
(2005/2012)
Installation time
From contract to commissioning
1-3 months* 6 months* 6 months* 6 - 9 months* 6 - 9 months*
Capacity
SC Net Output (MW)
31 MW (50Hz)
34.9 MW (60Hz)
32.5 MW (50Hz)
33.6 MW (60Hz)
53 MW 145 MW 185 MW (2005)
203 MW (2012)
Efficiency
SC Net Efficiency (%, LHV)
34.7% (50Hz)
36.5% (60Hz)
36.5% (50Hz)
38.4% (60Hz)
41.7% (50Hz)
41.8% (60Hz)
37% 37.8% (2005)
38% (2012)
Install base
Worldwide
207 units in 25 countries 2,130 units in 69 countries 1,216 units in 50+ countries 515 units in 44 countries 150 units in 34 countries
Operating experience
Hours
5 million 79 million 33 million 20 million 10 million
Fuel flexibility
Types
Standard fuels: natural gas, diesel, aviation
Non-standard fuels: propane, ethane, bio-diesel, ethanol, and naptha
Standard fuels: natural gas, diesel, aviation
Non-standard fuels: propane, ethane, bio-diesel, ethanol, and naptha
Standard fuels: natural gas, diesel, aviation
Non-standard fuels: propane, ethane, bio-diesel, ethanol, and naptha
The ultimate in fuel flexibility: can use more than 52 types of fuel Standard fuels: natural gas, diesel
* Assumes standard configuration and available inventory

FAST POWER SUCCESS STORIES

See how countries and organizations benefited from GE’s emergency and mobile power solutions. 

CONTACT GE TODAY

LET US HELP IDENTIFY THE POWER SOLUTION THAT BEST MEETS YOUR GROWING NEEDS

middle-east-egypt-adds-power.jpeg
Play Video

Fast Power for Egypt

Tanzania_3
Play Video

GE & Songas help Tanzania

Fast-Tracking Tunisia

GE can deliver permanent power solutions in 6-9 months. Our project in Tunisia is just one example. We’ll be providing a turnkey power plant project for Tunisian Electricity and Gas Company with two 9E.03 heavy-duty gas turbines, electrical balance of plant and service.

Read more about Tunisia  

Setting Records in Algeria

Algeria has faced a drastic need for more power, particularly during the hot summer months. Over the last three years, SPE, the power generation subsidiary of Sonelgaz, has partnered with GE and Power Projects Company (an affiliate of METKA) on contracts providing 38 trailer-mounted TM2500+ aeroderivative gas turbine generators.

Read more about Sonelgaz  

Power in Paradise: TM2500 in Greece

More than 2 million tourists flock to the Greek islands in summer alone, which puts a strain on the Greek power systems located on the small islands. Long-term and reliable power is difficult to maintain on an island.

Read more about Greece